Cyprus has one of the highest levels of solar irradiation in the European Union and, as an isolated electricity system without an operational interconnector, one of the most constrained grids. Curtailment of renewable generation connected to the distribution network, which is predominantly solar, reached 47% in 2025, up from 29% in 2024, according to CyprusGrid data reported by pv magazine. At the same time, the opening of the competitive electricity market, the end of net metering and net billing, and the arrival of co-located battery storage have changed how a solar photovoltaic (“PV”) park earns its revenue. For buyers, investors and lenders, legal due diligence on a Cyprus solar asset is therefore no longer a question only of licences and land title. It is equally a question of what the plant will be permitted to export, to whom it sells and on what terms.
This article sets out the principal Cyprus and EU law issues that arise on the acquisition of an operating solar PV park, whether structured as a share deal or an asset deal, and offers practical commentary on how those issues should be reflected in the transaction documents.
Key takeaways
Curtailment and grid-connection risk should be analysed at the outset and allocated expressly in the sale and purchase agreement (“SPA”) through warranties, a specific indemnity or the price mechanism.
Following market opening on 1 October 2025, the value of the park depends on its offtake contracts with licensed suppliers or aggregators, which should be reviewed as closely as the physical asset.
Land held by the project company must be reviewed under Cyprus property law, including the restrictions on acquisition of immovable property by third-country persons.
Merger control, FDI screening and, for larger transactions, the EU Foreign Subsidies Regulation may each impose a mandatory pre-closing approval.
Battery storage requires its own CERA licence and, in a financed project, almost always the consent of the lenders.
1. The legal and regulatory framework
Domestic legislation
The electricity sector is governed principally by the Law Regulating the Electricity Market (Law 130(I)/2021), which replaced the earlier Law 122(I)/2003 and transposed Directive (EU) 2019/944 on common rules for the internal market for electricity. It provides the licensing regime administered by the Cyprus Energy Regulatory Authority (“CERA”) for generation, supply and storage, and sets out the respective roles of the Electricity Authority of Cyprus (“EAC”), the Distribution System Operator (“DSO”) and the Transmission System Operator of Cyprus (“TSO”). Renewable generation is further governed by the legislation on the promotion and encouragement of the use of renewable energy sources, which transposes the Renewable Energy Directive, and by the regulatory decisions, market rules and grid codes issued by CERA and the system operators.
Planning and environmental consents are governed by the Town and Country Planning Law (Law 90/1972), the Streets and Buildings Regulation Law (Cap. 96) and the Law on the Assessment of the Effects on the Environment from Certain Projects (Law 127(I)/2018), which transposes Directive 2011/92/EU, as amended.
EU law as it applies in Cyprus
Three EU instruments are of particular relevance. First, Directive (EU) 2023/2413 (“RED III”) amended the Renewable Energy Directive to raise the EU’s 2030 renewables target and to accelerate permitting, including through renewables acceleration areas and maximum permit-granting periods. Secondly, the 2024 electricity market design reform, comprising Regulation (EU) 2024/1747 and Directive (EU) 2024/1711, promotes long-term power purchase agreements (“PPAs”) and requires public support for new generation to take the form of two-way contracts for difference, which will shape the offtake arrangements available to Cyprus projects. Thirdly, Regulation (EU) 2019/452 establishes the EU framework for the screening of foreign direct investment, implemented in Cyprus by the national screening law discussed below. EU regulations apply directly in Cyprus; directives take effect through national transposing legislation, and the stage of transposition should be confirmed at the time of the transaction.
2. Recent market changes and their effect on value
Three developments bear directly on the value of an operating park. First, the competitive electricity market opened on 1 October 2025. Revenue now depends on contracts with licensed suppliers or aggregators, or on participation in the organised markets, rather than on the arrangements previously in place with the EAC. Secondly, the net metering and net billing schemes ended on 31 December 2025 and were replaced from 1 January 2026 by a self-consumption framework designed by CERA. Thirdly, since January 2026 operating parks have been able to install co-located battery storage, although, as at March 2026, such storage could be charged only from the park’s own panels and could not participate in the day-ahead market.
3. Transaction structure: share deal or asset deal
Most operating parks are held through a special purpose vehicle and acquired by way of a share deal. A share deal leaves the licences, permits, connection agreement and contracts with the project company, subject to any change-of-control provisions and any notification or approval required by CERA or the counterparties. An asset deal, by contrast, requires the transfer or reissue of the licences, the novation of the connection agreement and principal contracts, and the transfer of the land or leasehold interest at the Department of Lands and Surveys.
The tax consequences differ materially, therefore, specialist tax advice should be obtained on the structure at an early stage.
4. Licences, permits and the grid connection
The starting point is the CERA licences for the construction and operation of the plant, together with the planning permit, building permit and any environmental approval. For each, the buyer should confirm that the licence is in force, that the installed capacity and technical configuration correspond to what was licensed, and that the conditions attached have been complied with. Variations in capacity, inverter configuration or site boundaries made after the licence was granted are a recurring source of non-compliance.
The connection agreement with the DSO or TSO and the plant’s curtailment record should be examined together. Historic generation data shows what the plant produced; it does not show what it will be permitted to export. The buyer should establish the basis on which curtailment is applied, whether any compensation is available, and whether the system operators’ published grid-development or storage plans are likely to improve or worsen the position.
Practical insight: general warranties that the plant has been operated in accordance with law offer limited protection against curtailment, which is usually lawful. Curtailment risk should be addressed specifically, whether through a price adjustment, an earn-out tied to exported volumes, or a specific indemnity.
5. Land, leases and real estate due diligence
The land review should confirm title to the site through searches at the Department of Lands and Surveys under the Immovable Property (Tenure, Registration and Valuation) Law (Cap. 224), and identify any mortgages, encumbrances, prohibitions or memoranda registered against it. Where the site is leased, the lease should extend beyond both the expected operating life of the plant and the tenor of any financing, should be capable of registration where the law permits, and should allow the assignment and security arrangements that a lender will require.
6. Offtake and revenue contracts
Where the plant sells under a PPA, supply contract or aggregation agreement, the price mechanism, duration, volume commitments, allocation of curtailment and imbalance costs, termination rights and change-in-law provisions deserve the same scrutiny as the physical asset. Contracts entered into before market opening should be checked for provisions that assumed the earlier arrangements and may now be unworkable. The creditworthiness of the offtaker and any credit support should also be assessed, as should whether the contract can be assigned by way of security to lenders.
7. Corporate due diligence on the project company
The corporate review covers the constitutional documents, the register of members and the share capital, the charges registered with the Registrar of Companies under the Companies Law (Cap. 113), the register of beneficial owners, existing financing, and any consents required on a change of control under the financing documents, the licences and the principal project contracts, including the EPC, operation and maintenance, and land agreements. Pending or threatened litigation, regulatory correspondence with CERA, and employment and health and safety matters should also be reviewed.
8. Regulatory approvals: merger control, FDI screening and foreign subsidies
Merger control
Under the Control of Concentrations between Undertakings Law (Law 83(I)/2014), a transaction that constitutes a concentration of major importance must be notified to, and approved by, the Commission for the Protection of Competition before it is implemented. The turnover thresholds are discussed in our article on merger control in Cyprus.
Foreign direct investment screening
Since 2 April 2026, the Establishment of a Framework for the Screening of Foreign Direct Investments Law of 2025 (Law 194(I)/2025) has also been in force. Notification to the Ministry of Finance, and its approval before implementation, are mandatory where a foreign investor acquires a participation of at least 25% in a business of strategic importance, which includes energy infrastructure, and the investment exceeds €2 million. A foreign investor is a natural person who is not a national of an EU Member State, an EEA State or Switzerland, or an undertaking of a third country. The use of an EU holding company does not by itself take a transaction outside the regime, since ownership and control higher up the structure are taken into account. The regime is examined in our article on the FDI screening framework in Cyprus.
9. Acquisition and project financing: the security package
The security customarily taken on the financing of a Cyprus solar PV project comprises: a pledge over the shares in the project company, which may qualify as a financial collateral arrangement under the Financial Collateral Arrangements Law (Law 43(I)/2004); a mortgage over the land under the Immovable Property (Transfer and Mortgage) Law (Law 9/1965), or security over the leasehold interest; an assignment by way of security of the receivables under the offtake and insurance contracts; charges over the project accounts; and direct agreements giving the lenders step-in rights under the principal project contracts.
On an acquisition, existing security must either be released at completion against repayment of the existing facilities or, where the debt is to remain in place, the lenders’ consent to the change of control must be obtained. Release mechanics, payoff letters and the timing of deregistration should be agreed well before completion.
10. Adding battery storage to an operating solar park
Owners are increasingly considering co-located battery energy storage systems to recover curtailed output. Under Law 130(I)/2021, the installation or operation of an electricity storage facility without a CERA licence is prohibited. Before equipment is ordered, the owner should confirm that the existing licences and connection agreement permit the installation, that the CERA licence and the planning and environmental permits for the storage facility can be obtained, and whether the lenders’ consent is required under the existing facility and security documents. The treatment of the additional revenue under the financing, the extension of the security package to the storage assets and the operating restrictions applicable to co-located storage should be agreed at the same time.
11. Protecting the buyer in the transaction documents
The findings of due diligence should be reflected in the price mechanism (locked box or completion accounts), specific warranties on licences, permits, grid connection, land and offtake, specific indemnities for identified risks such as unremedied permit breaches or curtailment, and conditions precedent for regulatory approvals and third-party consents. Warranty and indemnity insurance is increasingly used in renewable energy transactions in Cyprus to bridge the gap between a seller seeking a clean exit and a buyer seeking recourse, although known issues and curtailment are usually excluded from cover and must be dealt with directly in the SPA.
Conclusion
The acquisition of a Cyprus solar PV park now turns on the grid connection, the curtailment record and the offtake arrangements as much as on licences and land title. A buyer that identifies these issues early, reflects them in the price, warranties and conditions to completion, and plans for merger control, FDI screening and any storage investment from the outset will be best placed to secure the value it is paying for. Papakyriacou LLC advises investors, sellers and lenders on renewable energy transactions in Cyprus across its Corporate and M&A, Banking and Finance, Real Estate and Dispute Resolution practices.
The information contained in this article is provided for general information purposes only, reflects the legal and regulatory position as at the date of publication and does not constitute legal or professional advice. Specific advice should be obtained before acting on any matter discussed in this article.